South Korea breaks ground on 2.4 GW AI data center in Donghae

South Korea broke ground on Saturday (November 28) on GS Group's artificial intelligence data center in Donghae, Gangwon Province. President Lee Jae Myung attended the groundbreaking ceremony at the Bukpyeong No. 2 General Industrial Complex, alongside GS Group chairman Huh Tae-soo and Deputy Prime Minister and Minister of Science and ICT Bae Kyung-hoon. About 270 people attended, including lawmakers, officials, industry and academic representatives and local residents.

The campus will have 2.4 gigawatts (GW) of capacity once complete — the first phase, of 1.2 GW, is due to be completed in stages from 2028, with full operation targeted for 2029. It is the first gigawatt-scale AI data center to break ground under the South Korean government's three megaprojects, announced in June, and is expected to become one of Asia's largest AI infrastructure complexes. The estimated investment is about 30 trillion won (approximately US$22.4 billion), rising to as much as 120 trillion won including GPUs and memory chips.

Abundant power and seawater cooling

According to GS, the site was chosen for the region's abundant power generation capacity and the possibility of using seawater for cooling — two classic bottlenecks for data centers of this size. The company expects from hundreds to about 1,000 direct and indirect jobs after completion, with priority for local workers and data center training courses run with local universities.

Lee praised the speed of permitting — the key approvals were completed within three months — and said countries are fighting a “war without gunshots” over AI technology: falling a single step behind, he said, leaves a country a permanent follower, while stepping ahead can make it a leader that changes the game.

Part of an 8.4 GW plan

The Donghae project is one piece of South Korea's plan to build 8.4 GW of AI data center capacity in the first phase of the megaprojects, with SK, GS and Naver investing about 550 trillion won. Last week, Lee visited the construction site of SK's AI data center in Ulsan. Gangwon Province, the city of Donghae and GS signed a cooperation agreement on the project in July.

The Ministry of Science and ICT also published on November 20 a draft enforcement decree for the special act promoting the AI data center industry, which takes effect in March 2027. The draft exempts AI data centers outside the Seoul metropolitan area, up to 50 MW, from power grid impact assessments and sets up a one-stop permit process. A public hearing is scheduled for December 9, with opinions accepted until December 30.