A study published on Monday (November 16) by the Better Data Center Project estimates that Anthropic data centers in the United States will be powered in 2028 by about 87% natural gas and 11% coal. The figures are estimates by the group, not measurements. The Better Data Center Project is a nonprofit that campaigns for data centers to stop using fossil fuels, and its estimates rest on assumptions about how hard the data centers will run, cooling efficiency, and which grid plants will serve the added demand.
15 GW contracted and up to 38 million tons of CO2
According to the study, Anthropic had 15 GW of compute contracted as of October 2026, of which 5.9 to 9.6 GW are tied to specific data-center sites. On that basis, power-related CO2 emissions from Anthropic data centers would reach 17 to 38 million metric tons per year in 2028, with a mid-case of 32 million tons — above the total emitted by all of California's power plants in 2024, according to coverage of the study. The estimated carbon intensity is 1,033 to 1,076 lb CO2e per MWh, about 35% above the US grid average (767).
No renewable commitments in the US
The study also finds that Anthropic has made no direct renewable-energy commitments in the United States: its only publicly disclosed renewable commitments, contracts or investments are in Norway and Canada. It is the same buildout Geekiki already covered in November: Anthropic bought 1.7 GW of heavy-duty gas generators for US$ 3.4 billion to power its AI data centers. The study further estimates air-quality impacts — more than 13,000 tons of nitrogen oxides and 2,000 tons of fine particles per year — and US$ 2 to 3 billion a year in health damages.
To reach these figures, the group combined Epoch AI's compute tracker, Anthropic's announcements and filings and those of partners such as Amazon and SpaceX, and reporting by The Information and Semafor. The study does not claim the mix is final: without new renewable capacity commitments, the projection is that the added demand from Anthropic data centers will be met mostly by gas and coal.
Image: illustrative photo of a server room of the Worldwide LHC Computing Grid at CERN — not an Anthropic facility. Photo by Sashimi-b, Wikimedia Commons, CC BY.
Sources
- Better Data Center Project — How AI is powered: a breakdown of BYOP and grid power
- DEV Community / Fathom News — Anthropic's Data Centers Could Out-Pollute California's Power Plants
- LavX News — Anthropic's data center buildout could emit up to 38 million tons of CO2 a year by 2028, analysis finds
Earlier Geekiki coverage: Anthropic gasta US$ 3,4 bi em geradores a gás 1,7 GW para data centers de IA
Transparency note: this article was produced with the assistance of artificial intelligence, cross-checked against public posts on X and internet sources, and reviewed before publication. Please consult the original sources to confirm the information.
By Muse